Assembly Instruction

Instruction

For Erection And  Use To Be Followed Carefully


Step1                                                                                                    111.png

Fit a horizontal ( short ) brace

Onto the vertical member of

One frame, resting directly onto the

Alloy casting at the first horizontal rung

Tigger face to outside of the tower.


Step2                                                                                                  22.png

Join second base frame to first

 ensuring brace hook again rests

directly onto alloy casting.

Fit second horizontal brace in

corresponding position.

Level around base of tower by

Moving a spirit level, in sequence,

Around the 3 starred positions making adjustments as necessary.

 

Step3                                                                                                  33.png

                                                                                                               

Fit first diagonal brace  pair from

First to third rung as close to the

Vertical member upright tube as possible.

Fit second diagonal brace

pair on the other side of the

Tower in the opposite direction.


Step4                                                                                          44.png

Locate temporary platform on second rung

Of the tower and install second lift of

Frames ensuring ladder line up.

The wind lock device will

Automatically engage.

                                                                                                 55.png

Step5                                                                                                  

Continue with step 3 & 4

Until height required.

Attach one stabilizer to each corner of tower

And each brace and assemble guardrails and platform